In late December 2012 when the conical drilling rig ‘Kulluk’, 9,900 DWT, was under tow to Seattle the tow connection parted in a severe storm in the Gulf of Alaska. Despite efforts to re-establish the tow connection the rig eventually grounded on the pristine coast of Sitkalidak Island, which is part of Kodiak Island.

The severe weather, condition of the rig, remote location and the fact that the rig was located in one of America’s most sensitive environments meant that a successful salvage operation was given the highest priority. It was vital to prevent further harm to the environment and a swift refloat was required to avoid any additional damage to the specialized rig. The owners of the Kulluk contracted SMIT Salvage under a LOF contract to perform this exceptionally challenging task.

Although flight availability was scarce due to the holiday period and aircraft types were restricted because of the remote location and suitable airstrips on Kodiak Island, the first team of salvage experts were mobilized and brought into Alaska by a chartered plane. Additional salvage crew consisting of engineers, naval architects and shore support followed shortly hereafter. After the salvage team inspected the rig a salvage plan was submitted and approved by the owners, local authorities and the US Coast Guard. By utilizing SMIT’s Dyneema towing lines the casualty was successfully refloated on January 6th, 2013.

After refloating the rig it was towed to a sheltered location where a dive survey was conducted to assess the damage. After a thorough assessment by the salvors, showing no major damage, the rig was redelivered to its owners. SMIT Salvage continued its operation by assisting the owners with extensive preparations for onward towage to Dutch Harbor, Alaska. Once it had safely arrived there, the rig was loaded onto a heavy transport vessel on the 19th of March for onward transport to Singapore where the same salvage team, supported by Smit’s Singapore organization, unloaded the rig from the heavy transport vessel.

Related projects

Selected filters
SMART-0903

Smart

During heavy swells on the morning of the 19th of August the bulk carrier 'Smart', 150,000 DWT loaded with 147,000 tons of coal, left the port of Richards Bay, South Africa heading for China. Soon, however, the swell became too much and the vessel grounded next to the channel, less than 250 m from the coast. Just hours after the grounding, the vessel broke in two.

USS_Guardian

USS Guardian

On the 29th of January the ‘USS Guardian’, a mine countermeasures ship of the US Navy, grounded on the North Western tip of the Tubbataha Reef in the Sulu Sea. The prevailing North East monsoon, sea and swell impacting on the vessel were causing her to move up on the reef and she was deteriorating, hence a swift operation was required to avoid the risk of pollutants being released into the environment.

Jin_Tai

Jin Tai

The beginning of 2012 involved the salvage case of the backacter bucket dredger ‘JIN TAI’. This backhoe dredger was working on the construction and expansion of the newly built container port of Coega near Port Elizabeth (South Africa), when it experienced a problem with one of the vessels’ legs. A cable attached to one of the three spud piles came loose, causing one of the legs to give way and the engine room start flooding.

Kulluk_BP_2_2013

Kulluk

In late December 2012 when the conical drilling rig ‘Kulluk’, 9,900 DWT, was under tow to Seattle the tow connection parted in a severe storm in the Gulf of Alaska. Despite efforts to re-establish the tow connection the rig eventually grounded on the pristine coast of Sitkalidak Island, which is part of Kodiak Island.

Rig_Noble_Regina_Allen_1_2012

Rig Noble Regina Allen

In December 2012 the newly built rig 'Noble Regina Allen', constructed at Jurong Shipyard Singapore, was undergoing operational tests. The jack-up rig suffered from a mechanical failure on one of the jacking systems during the pre-load test. This failure resulted in the rig tilting severely and the bow section submerging into the sea until the rig came to rest on the seabed.

Chamarel_2012

Chamarel

The French cable-laying vessel 'Chamarel', 5,900 DWT, suffered an engine room fire off the Namibian coast, which spread rapidly and eventually burnt down the accommodation. The vessel drifted to shore were it grounded on the sandy beach of the Skeleton Coast, a very remote location.