On Thursday evening 30 July 2009 bulk carrier ‘Full City', 26,758 DWT (in ballast and at anchor off the port of Langesund, Norway, awaiting her berth) was trapped in a sudden storm, causing her anchor to drag, and came to rest on the rocks.

The engine room flooded and the double bottom fuel oil tanks breached which resulted in a major spill. Subsequently, the Norwegian Coastal Administration (NCA) mobilised all available crafts, oil barriers/ booms and anti-pollution equipment in order to battle the pollution.

SMIT Salvage contracted by owners
In the early morning of Friday 31 July, SMIT Salvage was contracted by the owners under a Lloyd's Open Form 2000 Scopic contract. SMIT's Norwegian partner tug and salvage company Buksér og Berging (B&B) was taken on as subcontractor. SMIT and B&B have a longstanding relationship and worked together on several projects such as the ‘Rockness' and most recently in December 2008 the ‘Crete Cement'.

Mobilisation
A salvage team from Rotterdam was immediately mobilised by charter plane, arriving on-site on Friday afternoon. The most essential salvage, pumping and fuel oil recovery equipment was airlifted as well. In the meantime, SMIT and B&B mobilised the DSV ‘BIG', tugs and a tank barge, while the NCA kept on site Coastguard vessel ‘Nornen' and tug ‘Balder'. Salvage operationThe salvage team recovered all remaining heavy fuel oils and other pollutants out of the holds and tanks by means of skimming and pumping. The recovered pollutants were transported to shore and disposed of. Following this, the damaged holds could be repaired. The vessel was then de-ballasted in preparation for a refloating attempt. With the assistance of three B&B tugs, the vessel was successfully refloated in the morning of Monday 17 August. Accordingly, SMIT Salvage towed the ‘Full City' to a more sheltered, deep-water NATO jetty at a distance of approximately nine miles from the grounding site. Upon arrival, in the late afternoon, the salvage team performed a final diving survey after which the vessel was redelivered to the owners.

Related projects

Selected filters
MSC_Napoli_3

MSC Napoli

Container ship ‘MSC Napoli' suffered severe damage during a violent storm in the English Channel on 18 January 2007. SMIT Salvage was contracted to salvage the vessel which involves the discharge of all 2300 containers and the ultimate refloating of the vessel.

dina_barge

Dina Barge

'Dina Barge' (diameter: 120 x 33.5 x 7.6 m), laden with a cargo of 12 hulls (6500 tons ttl), was on route from the Far East to Europe when, during severe monsoon conditions, it broke off from the main vessel 'YM Shanghai'. It finally ran aground 90 km south of Mumbai (India).

UND_1

UND Adriyatik

Ro-ro vessel ‘UND Adriyatik' was suffering from a fire on board, off the coast of Pula, Croatia.

Mighty_Servant_3

Mighty Servant 3

In the morning of 6 December 2006 semi submersible vessel 'Mighty Servant 3' developed a list and sank off the port of Luanda, Angola, after the offloading of drilling platform ‘Aleutian Key'.

Ocean_Warwick_Rita

Hurricane Rita

Shortly after Hurricane Katrina, a weakened but still powerful Hurricane Rita altered its course to threaten residents in Louisiana and Texas. Rita was the fifth major hurricane in the U.S.A. of that season.

Selendang_Ayu

Selendang Ayu

The Malaysian flagged 225 metres long cargo vessel suffered a main engine breakdown, drifted without power, grounded and eventually broke in two off the coast of Western Unalaska Island.